Opened 3 years ago

Last modified 2 years ago

#2617 assigned defect

Saved searches not updated in REDCap projects after Arkansas release

Reported by: tmcmahon Owned by: dconnolly
Priority: minor Milestone: heron-menomonee-update
Component: data-repository Keywords: public-web redcap-to-heron
Cc: ngraham, mhoag, dconnolly, badagarla, vleonardo, tmcmahon Blocked By: 2646
Blocking: Sensitive: no

Description

Vince had searches saved in his vleonardo folder of the REDCap project within HERON. After the Arkansas release, the searches disappeared. Did search history get backed-up for the REDCap projects within HERON? Can he get access to those searches?

Change History (30)

comment:1 Changed 3 years ago by ngraham

Yes, past queries were restored (at least, by design). I suspect it's something about permissions - Vince and I were able to find a previous query in the qt_query_master at least: "Q1-COPD Banded Date Ranges - Both Test Groups". This query doesn't show up when we log in to HERON.

comment:2 Changed 3 years ago by ngraham

  • Owner changed from ngraham to badagarla
  • Status changed from new to assigned

Bhargav,

Assigning to you as you mentioned to me that you're figuring out the priority of this with Dan/Russ.

I think work may overlap with (or is at least related to):

comment:3 Changed 3 years ago by dconnolly

  • Component changed from dev-framework to data-repository

comment:4 Changed 3 years ago by vleonardo

  • Cc vleonardo. tmcmahon added; vleonardo removed

comment:5 Changed 3 years ago by vleonardo

  • Cc vleonardo added; vleonardo. removed

comment:6 Changed 3 years ago by vleonardo

Tamara has showed me how to increase the number of queries in my 'working list'.  This has allowed me to go back and find my older queries and then I can re-save them to the shared workspace.   I would need to do this after every release but it's a viable work-around until a solution can get worked out.

comment:7 Changed 3 years ago by ngraham

  • Keywords public-web added
  • Sensitive unset

comment:8 Changed 3 years ago by dconnolly

  • Milestone changed from heron-kirwan-update to heron-marmaton-update

BA reports VL has a work-around
TM is OK with Marmaton timeframe.

comment:9 Changed 3 years ago by dconnolly

  • Blocked By set to 2646
  • Milestone changed from heron-marmaton-update to heron-hackberry-update

This should be addressed by the design in ticket:2646#comment:17, which was scheduled for July in HeronProjectTimeline#May2014Planning.

comment:10 Changed 3 years ago by dconnolly

  • Keywords redcap-to-heron added

comment:11 Changed 3 years ago by dconnolly

postponed in HeronLoad#milestone-plan meeting along with #2646

comment:12 Changed 3 years ago by ngraham

  • Milestone changed from heron-hackberry-update to heron-wakarusa-update

In the Hackberry milestone meeting, we postponed.

comment:13 Changed 3 years ago by ngraham

  • Milestone changed from heron-wakarusa-update to heron-delaware-update

comment:14 Changed 3 years ago by ngraham

  • Owner changed from badagarla to dconnolly

comment:15 Changed 3 years ago by ngraham

  • Priority changed from major to minor

Demoted in HERON planning meeting today.

comment:16 Changed 3 years ago by dconnolly

  • Milestone changed from heron-delaware-update to heron-saline-update

comment:17 Changed 3 years ago by dconnolly

  • Milestone changed from heron-saline-update to heron-verdigris-update

This REDCap stuff was postponed in discussion with Russ, Tamara, etc. today.

comment:18 Changed 3 years ago by dconnolly

  • Milestone changed from heron-verdigris-update to heron-kanopolis-update

postponing tickets other than those identified as Verdigris priorities in today's heron-weekly meeting

comment:19 Changed 3 years ago by dconnolly

  • Milestone changed from heron-kanopolis-update to dconnolly

Milestone renamed

comment:20 Changed 3 years ago by dconnolly

  • Milestone changed from dconnolly to heron-kanopolis-update

Milestone renamed

comment:21 Changed 3 years ago by dconnolly

  • Milestone changed from heron-kanopolis-update to dconnolly

Milestone renamed

comment:22 Changed 3 years ago by dconnolly

  • Milestone changed from dconnolly to heron-kanopolis-update

Milestone renamed

comment:23 Changed 3 years ago by dconnolly

  • Milestone changed from heron-kanopolis-update to heron-webster-update

closing Kanopolis, postponing remaining minor tickets without discussion

comment:24 Changed 3 years ago by dconnolly

  • Milestone changed from heron-webster-update to heron-mcmillan-marsh-update

REDCap integration redesign (#2646) scheduled for March in HeronProjectTimeline#Jan2015Planning

comment:25 Changed 3 years ago by dconnolly

  • Milestone changed from heron-mcmillan-marsh-update to heron-quivira-update

postpone these REDCap integration tickets along with the main one, #2646, which was postponed in March 11 heron-weekly.

comment:26 Changed 2 years ago by mhoag

  • Milestone changed from heron-quivira-update to heron-jamestown-update

Ticket retargeted after milestone closed

comment:27 Changed 2 years ago by ngraham

  • Milestone changed from heron-jamestown-update to heron-calhoun-update

Ticket retargeted after milestone closed

comment:28 Changed 2 years ago by ngraham

  • Milestone changed from heron-calhoun-update to heron-riverwalk-update

Ticket retargeted after milestone closed

comment:29 Changed 2 years ago by dconnolly

  • Milestone changed from heron-riverwalk-update to heron-michigan-update

move with #2646

comment:30 Changed 2 years ago by dconnolly

  • Milestone changed from heron-michigan-update to heron-menomonee-update

bumping minor technical debt (or similar)

Note: See TracTickets for help on using tickets.